On time and UNDER budget!

The 2012 bond is almost wrapped up. Once again, Jeffco’s facilities management team delivered the work on time, delivered all the promised work, and more, within the total budget.

http://www.jeffcopublicschools.org/fmp/2012_bond_spent.pdf

You’ll remember that the 2012 Bond addressed only the most critical needs of the district, to keep our students warm, safe and dry. Please note that there remains over $1.2 Billion dollars in current needs. Clearly, our Jeffco team does an amazing job in pinching every penny of taxpayer dollars to do as much as they can for our students every day.

This district can accomplish an impressive list of work that impacts all students when supported by voters. Take a look at what that support from 2012 achieved for students and our community:

ARTICULATION AREA – ALAMEDA

  • Deane: HVAC system renovation, Electrical system repairs, Added Scope Security system Improvements
  • Kendrick Lakes: Security system partial replacement, Sidewalk repair
  • Lasley: HVAC system renovation, Fire alarm & security system replacement, Added Scope Sidewalk repair
  • Patterson International: Security system partial replacement, Added Scope Water Heater & Piping
  • Stein Elementary: Security system partial replacement, Exterior envelope repairs
  • O’Connell: Security system and paging system upgrades, Added Scope HVAC system renovation
  • Alameda: Fire alarm & security system upgrade, Sidewalk repair

ARTICULATION AREA – ARVADA

  • Arvada K-8: Electrical system partial replacement, Additional exterior envelope restoration, Fire alarm & security system replacement, Added scope concrete & paving
  • Fitzmorris: Exterior envelope upgrades, HVAC system renovation
  • Foster: Additional exterior envelope restoration, Fire alarm & security system replacement, Added Scope Parking Lot Replacement
  • Hackberry Hill: Electrical system partial replacement
  • Lawrence: Fire alarm, paging & security system replacement, Exterior envelope restoration, Boiler replacement
  • Peck: Exterior envelope restoration, Fire alarm & security system replacement, HVAC partial replacement, Roof replacement
  • Secrest: Additional exterior envelope restoration, Fire alarm, paging & security system replacement, HVAC partial replacement; Added scope concrete & paving
  • Swanson: Additional exterior envelope restoration, Fire alarm, paging & security system replacement, HVAC partial replacement, Sidewalk repair/replacement
  • Thomson: Exterior envelope restoration, Roof replacement, Sidewalk repair/replacement
  • North Arvada: Bleacher repair/replacement, Exterior envelope restoration  Fire alarm, paging & security system replacement, HVAC unit replacement  Roof replacement
  • Arvada: Bleacher repair/replacement, Electrical system renewal, Additional HVAC system renovation, Security system upgrade

ARTICULATION AREA – ARVADA WEST

  • Allendale: HVAC system renovation, Security system replacement
  • Campbell: Exterior envelope restoration, Fire alarm & security system replacement, HVAC system renovation, Added Scope sidewalk repair
  • Fairmount: Exterior envelope restoration, Partial HVAC system renovation
  • Fremont: Additional exterior envelope restoration, Fire alarm & security system replacement, HVAC system renovation
  • Stott: Fire alarm & security system replacement, HVAC system renovation  Added Scope sidewalk repair
  • Vanderhoof: Electrical system partial replacement, HVAC partial replacement, Added Scope sidewalk repair
  • Drake: Exterior envelope restoration, HVAC partial replacement, Partial roof replacement, Added Scope bleacher replacement, Added Scope sidewalk repair

ARTICULATION AREA – BEAR CREEK

  • Bear Creek: K-8 No critical needs
  • Green Gables: Water heater replacement, Security system panel replacement
  • Kendallvue: Fire alarm system renovation, Sidewalk repair/replacement
  • Peiffer: Additional exterior envelope restoration, Fire alarm & security system renovation, HVAC system renovation, Added Scope Sidewalk repair/replacement
  • Red Rocks: Electrical system repair
  • Westgate: Additional HVAC system renovation, Security system replacement, Added Scope Sidewalk repair/replacement
  • Carmody: Bleacher repair/replacement, Fire alarm & security system replacement, HVAC system renovation, Plumbing system restoration

ARTICULATION AREA – CHATFIELD

  • Bradford Intermediate: Fire alarm & security system replacement, HVAC system renovation, Roof replacement, Added Scope Parking lot & sidewalk repair/replacement
  • Bradford Primary: Additional HVAC system renovation, Added Scope Sidewalk repair/replacement
  • Coronado: HVAC system renovation, Parking lot & sidewalk repair/replacement
  • Mortensen: Exterior envelope restoration, HVAC system renovation, Roof replacement, Added Scope Parking lot & sidewalk repair/replacement
  • Shaffer: Exterior envelope restoration, Parking lot & sidewalk repair/replacement
  • Stony Creek: Electrical system partial replacement, HVAC system renovation,  Sidewalk repair/replacement
  • Ute Meadows: Electrical system partial replacement, HVAC system renovation, Sidewalk repair/replacement, Site drainage system restoration
  • Deer Creek: Bleacher repair/replacement, Backup chiller repair/replacement  Roofing partial replacement, Paging system partial replacement, Added Scope Sidewalk repair/replacement
  • Chatfield: HVAC system renovation, Roof replacement, Sidewalk repair/replacement

ARTICULATION AREA – COLUMBINE

  • Columbine Hills: Additional exterior envelope restoration, HVAC system renovation, Roofing partial replacement
  • Columbine Preschool: Surplus cottage B & C and temp June 2012, No critical needs in cottage A
  • Dutch Creek: Fire alarm & security system replacement, HVAC system partial replacement, Added Scope Sidewalk repair/replacement
  • Governor’s Ranch: Additional exterior envelope restoration
  • Leawood: Fire alarm & security system replacement, HVAC system renovation, Sidewalk repair/replacement
  • Normandy: HVAC system renovation, Sidewalk repair/replacement
  • Ken Caryl: Bleacher repair/replacement, Exterior envelope replacement,  Water heater replacement
  • Columbine: Fire alarm & security system replacement, HVAC system renovation, Water heater replacement, Exterior envelope restoration

ARTICULATION AREA – CONIFER

  • Elk Creek: HVAC system renovation, Fire hydrant replacement Septic system restoration in progress
  • Marshdale: Electrical transformer replacement, Sidewalk repair
  • West Jefferson: Electrical system partial replacement, Domestic water system restoration
  • West Jeff Preschool: Decommissioned June 2012
  • West Jefferson: Additional exterior envelope restoration, Fire alarm, paging & security system replacement, HVAC system renovation, Partial roof replacement, Bleacher repair/replacement
  • Conifer: Elevator upgrade, Fire alarm, paging & security system replacement,  Paving & concrete replacement, Water & wastewater treatment plant upgrades

ARTICULATION AREA – DAKOTA RIDGE

  • Blue Heron: HVAC system renovation, Security system panel replacement
  • Colorow: Water heater replacement, Sidewalk repair/replacement, Added Scope Security System Improvements
  • Mount Carbon: Fire alarm, paging & security system replacement, HVAC system renovation
  • Powderhorn: Fire alarm, paging & security system replacement
  • Westridge: Exterior door & hardware replacement, Added Scope Security System Improvements
  • Summit Ridge: Paging & security system replacement
  • Dakota Ridge: Bleacher replacement, Fire alarm & security system replacement, HVAC system renovation, Roof replacement

ARTICULATION AREA – EVERGREEN

  • Bergen Meadow: Fire alarm & security system replacement, Additional HVAC system renovation
  • Bergen Valley: Roof replacement, Security system panel replacement, Added Scope Sidewalk repair/replacement
  • Parmalee: Exterior door & hardware replacement, HVAC system renovation  Septic system restoration
  • Wilmot: HVAC system renovation, Sidewalk repair/replacement
  • Evergreen: Partial HVAC system renovation, Sidewalk repair/replacement High Schools
  • Evergreen: Elevator repair/replacement, Fire alarm & security system replacement, Additional HVAC system renovation, Locker replacement

ARTICULATION AREA – GOLDEN

  • Kyffin: Power services upgrade, Security system partial replacement
  • Mitchell: Fire alarm & security system replacement, HVAC system renovation
  • Pleasant View: Exterior envelope restoration, HVAC system renovation  Paging & security system replacement, Sidewalk repair/replacement
  • Ralston: Exterior door replacement, HVAC system renovation
  • Shelton: HVAC system renovation, Paging & security system replacement
  • Welchester: Electrical panel replacement, Exterior door hardware replacement, HVAC system renovation
  • Bell: Bleacher repair/replacement, Paging & security system replacement, HVAC system renovation, Paving replacement

ARTICULATION AREA – GREEN MOUNTAIN

  • Devinny: Door hardware replacement, Paging system replacement, HVAC system partial renovation, Added Scope Roof Replacement
  • Foothills: Security system panel replacement, Sidewalk repair/replacement
  • Green Mountain: Additional exterior envelope restoration, HVAC system partial renovation
  • Hutchinson: HVAC system partial renovation, Fire alarm & security system replacement
  • Rooney Ranch: HVAC system partial renovation, Partial roof replacement
  • Green Mountain: Bleacher repair/replacement, HVAC system partial renovation, Security system replacement

ARTICULATION AREA – JEFFERSON

  • Edgewater: Exterior door & hardware replacement, HVAC system partial renovation, Sidewalk repair/replacement
  • Lumberg: Exterior door & hardware replacement, Fire alarm, paging & security system replacement, Roof replacement, Sidewalk repair/replacement
  • Martensen Declared surplus – to be sold July 2012
  • Molholm: Fire alarm & security system replacement, HVAC system partial renovation, Sidewalk repair/replacement
  • Stevens K-4: Exterior door hardware replacement
  • Wheat Ridge 5-8: Bleacher repair/replacement, Security system replacement
  • Jefferson: Exterior door replacement, Fire alarm & paging system replacement, Sidewalk repair/replacement

ARTICULATION AREA – LAKEWOOD

  • Belmar: Electrical switchgear replacement, HVAC system partial renovation  Roof replacement, Security system replacement
  • Eiber: Exterior envelope restoration, HVAC system partial renovation  Paging & security system replacement, Sidewalk repair/replacement
  • Glennon Heights: Fire alarm, paging & security system replacement, Partial HVAC system renovation, Roofing partial replacement
  • Slater: Fire alarm & security system replacement, HVAC system partial renovation, Roofing partial replacement, Water heater replacement
  • South Lakewood: Paging system replacement
  • Creighton: Bleacher repair/replacement, Sidewalk repair/replacement
  • Lakewood: Auditorium stage/theater lighting replacement, Upper bleacher repair/replacement, HVAC system partial renovation

ARTICULATION AREA – POMONA

  • Little: Exterior door hardware replacement, Paging system replacement, Water heater replacement
  • Parr: Exterior door & hardware replacement, Security system replacement
  • Warder: HVAC system renovation, Roof replacement
  • Weber: HVAC system renovation
  • Zerger: Decommissioned
  • Moore: Exterior door replacement, Fire alarm & security system replacement
  • Pomona: HVAC system partial renovation, Paging system replacement, Site drainage restoration

ARTICULATION AREA – RALSTON VALLEY

  • Coal Creek Canyon K-8: HVAC system partial renovation, Security system replacement, Sidewalk repair/replacement
  • Sierra: Security system replacement
  • Van Arsdale: Paving repair/replacement
  • West Woods: Exterior envelope restoration
  • Oberon: Boiler replacement, Security system panel replacement
  • Ralston Valley: Exterior envelope restoration, Partial HVAC system renovation, Security system replacement

ARTICULATION AREA – STANDLEY LAKE

  • Adams: Exterior door replacement, HVAC system partial renovation, Added Scope Sidewalk repair/replacement
  • Lukas: Exterior door replacement, HVAC system & controls partial renovation,  Added Scope Sidewalk repair/replacement
  • Ryan: Paging system replacement
  • Semper: Electrical system renovation, Paging system replacement, Added Scope Fire Alarm Improvements, Added Scope Roof Improvements
  • Sheridan Green: Electrical system renovation, Added Scope HVAC Improvements
  • Witt: Fire alarm & security system replacement, HVAC system partial renovation
  • Mandalay: Bleacher repair/replacement, Added Scope Exterior Envelope Improvements, Added Scope Sidewalk repair/replacement
  • Standley Lake: Bleacher replacement, Paging & security system replacement, Added Scope Exterior Envelope Improvements

ARTICULATION AREA – WHEAT RIDGE

  • Kullerstrand: Fire alarm & security system replacement, HVAC system partial renovation, Added Scope-Paving/Concrete
  • Maple Grove: Exterior envelope restoration, Fire alarm & security system replacement, HVAC system partial renovation
  • Pennington: Exterior envelope restoration, HVAC system partial renovation, Added Scope-Paving/Concrete
  • Prospect Valley: Security system panel replacement
  • Stober: Fire alarm, paging & security system renovation
  • Vivian: Fire alarm & security system replacement, HVAC system partial renovation, Sidewalk / site access repair & replacement
  • Wilmore-Davis: Paging system replacement, HVAC system partial renovation, Added Scope-Paving/Concrete
  • Everitt: Additional exterior envelope restoration, HVAC system partial renovation, Paving repair/replacement
  • Wheat Ridge: Security alarm replacement

CHARTER SCHOOLS

  • Collegiate Academy: HVAC system partial renovation, Exit & emergency lighting replacement, Exterior door replacement, Sidewalk replacement & drainage improvements
  • Compass Montessori – Golden: HVAC system partial renovation, Exterior door and window replacement, Exterior envelope insulation installation
  • Compass Montessori – Wheat Ridge: Exterior door replacement, Exterior insulation installation & gutter replacement
  • Excel Academy: Partial roof repair & drain installation, Install eyewash station in science lab
  • Free Horizon: Gas fired/DX roof top unit replacement, Emergency lighting replacement
  • Jefferson Academy: Exterior door and window replacement, Boiler replacement
  • Lincoln Academy: Exterior doors, stairs & window replacement– Bldg. A,  Emergency & exit light replacement-Bldg. A, HVAC system partial renovation
  • Montessori Peaks Academy: HVAC controls replacement, Public address system installation, Emergency lighting installation/replacement
  • Mountain Phoenix of Wheat Ridge: Building A boiler replacement, Building A Emergency Lighting, Building A Tuckpoint Chimney, PreK Building Update Fire Alarm, PreK Building Replace 4 Windows, Site Fencing (Secure Perimeter of Property)
  • Rocky Mountain Academy – Evergreen: Address site drainage between buildings & N side
  • Rocky Mountain Deaf School No items included in bond proposal
  • Woodrow Wilson Academy: Exterior Glazing High Bay Areas, Roofing Repairs Elementary School, Fire Alarm Repair/Replace, Emergency Lighting/Battery Pack

DISTRICTWIDE / OPTION SCHOOLS

  • Brady Exploration School & Literacy Center Preschool: Electrical power service & panel replacement, HVAC system partial renovation, Roof replacement
  • Dennison Elementary School: Additional exterior envelope, Fire alarm & security system replacement, HVAC system partial renovation, Partial roof replacement
  • D’Evelyn Junior/Senior HS: Chiller & cooling tower Jeffco Open School, Water heater replacement
  • Long View HS: Exterior lighting replacement
  • Manning School: Exterior envelope restoration, Roof & skylight replacement, Security system replacement
  • Fletcher Miller Special: Fire alarm & security system replacement
  • Sobesky Academy: Exterior door replacement, Security system replacement, Added Scope-Paving/Concrete
  • Warren Occupation Technical Center (OTC) High School: Electrical transformer replacement, HVAC system partial replacement, Added Scope-Paving/Concrete
  • Warren OTC North Campus: HVAC system partial replacement

OUTDOOR EDUCATION LAB SCHOOLS

  • Mt. Evans OELS: Emergency lighting replacement
  • Windy Peak OELS: Emergency lighting replacement, Fire sprinkler replacement

ADMINISTRATION, STADIA, AND SUPPORT FACILITIES

  • Education Center No critical needs funded
  • JeffCo Stadium – Driving Education Center No critical needs funded
  • Jefferson County Stadium No critical needs funded
  • Lakewood Memorial Stadium No critical needs funded
  • North Area Athletic Complex No critical needs funded
  • North Transportation Center No critical needs funded
  • Shop Facility for Zones 1 & 2 No critical needs funded
  • South Transportation Center No critical needs funded
  • Support Services No critical needs funded
  • Trailblazer Stadium No critical needs funded
  • West Transportation No critical needs fund

We Support Jeffco Kids and THIS is why we have endorsed 3A & 3B!

#WeAreJeffco